01. Name of Project |
Construction of Transitional Houses. |
02. District Operation |
Ampara |
03. Divisional Secretariat Divisions |
Coastal area. |
04. Village |
Coastal area. |
05. Implementing Partner |
GAFSO (Group Action for Social Order.) |
06. Funded by |
Relief International. |
07. Period/Date Commenced/Completed |
Commencement |
Completion |
January, 2005 |
April, 2005 |
08. Number of beneficiaries |
100 houses |
09. Number of Officers engaged |
20 |
10. Objectives
- To provide shelter to Tsunami victims
- Water and sanitation
- Possible electricity supply
- Structure Last for 3 years
|